Project MR533/TJ000201/GLM - Activities implemented for April, May and beginning of June 2008
The continuation of the work on the construction of the channel from Dariyakul Lake to Hudoykul channels:
1. Preparation for transportation and repair of the excavator dragline-652. - Duration - 7 days. 2. Transportation of the excavator on trailer. – Distance 120 km. (there and back) – duration - 1 day 3. Work on the construction of the channel - sinking 0.7 km. – duration 15 days 4. Delivery GSM to place of work- 7 days. – Distance - 30 km h 7 days = 210 km 5. Transportation of technical staff to the place of work (there - back) daily. - distance 15 km. total 150 km. 6. Transportation of the excavator dragline - 3211 (marsh) on trailer. The distance 140 km (there and back). Duration - 1 day. 7. The work on the construction of the channel. Sinking – 0.8 km.
|
|
|
| Статьи |
|
| Опрос |
| Готовы ли Вы участвовать в развитии проекта? |
|
| Отчеты |
|
| Скачать файлы |
|
| Вид из космоса |
|
|
|